Our pass rate is high to 98.9% and the similarity percentage between our CAPM study guide and real exam is 90% based on our seven-year educating experience. Do you want achievements in the PMI CAPM exam in just one try? I am currently studying for the PMI CAPM exam. Latest PMI CAPM Test exam practice questions and answers, Try PMI CAPM Brain Dumps First.
Also have CAPM free dumps questions for you:
NEW QUESTION 1
In an organization with a projectized organizational structure, who controls the project budget?
- A. Functional manager
- B. Project manager
- C. Program manager
- D. Project management office
Answer: B
NEW QUESTION 2
When a backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during a forward pass calculation, this causes which type of total float?
- A. Negative
- B. Zero
- C. Positive
- D. Free
Answer: C
NEW QUESTION 3
Organizational process assets, a lessons-learned database, and historical information are all inputs to which process?
- A. Plan Cost Management
- B. Plan Scope Management
- C. Plan Stakeholder Management
- D. Plan Schedule Management
Answer: C
NEW QUESTION 4
In which Knowledge Area is the project charter developed?
- A. Project Cost Management
- B. Project Scope Management
- C. Project Time Management
- D. Project Integration Management
Answer: D
NEW QUESTION 5
Which earned value management (EVM) metric is a measure of the cost efficiency of budgeted resources expressed as a ratio of earned value (EV) to actual cost (AC) and is considered a critical EVM metric?
- A. Cost variance (CV)
- B. Cost performance index (CPI)
- C. Budget at completion (BAC)
- D. Variance at completion (VAC)
Answer: B
NEW QUESTION 6
Prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact takes place in which process?
- A. Monitor and Control Risks
- B. Plan Risk Management
- C. Perform Qualitative Risk Analysis
- D. Perform Quantitative Risk Analysis
Answer: C
NEW QUESTION 7
Which Process Group typically consumes the bulk of a project's budget?
- A. Monitoring and Controlling
- B. Executing
- C. Planning
- D. Initiating
Answer: B
NEW QUESTION 8
Which type of elaboration allows a project management team to manage at a greater level of detail as the project evolves?
- A. Cyclic
- B. Progressive
- C. Repetitive
- D. Iterative
Answer: B
NEW QUESTION 9
Which of the following outputs from the Control Schedule process aids in the communication of schedule variance (SV), schedule performance index (SPI), or any performance status to stakeholders?
- A. Performance organizations
- B. Schedule baselines
- C. Work performance measurements
- D. Change requests
Answer: C
NEW QUESTION 10
Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?
- A. Reserve analysis
- B. Three-point estimating
- C. Parametric estimating
- D. Analogous estimating
Answer: D
NEW QUESTION 11
At which point of the project is the uncertainty the highest and the risk of failing the greatest?
- A. Final phase of the project
- B. Start of the project
- C. End of the project
- D. Midpoint of the project
Answer: B
NEW QUESTION 12
Which of the following types of a dependency determination is used to define the sequence of activities?
- A. Legal
- B. Discretionary
- C. Internal
- D. Resource
Answer: B
NEW QUESTION 13
The project manager notes that stakeholders are aware of the project and potential impacts and are actively engaged in ensuring that the project is a success. The engagement level of the stakeholders should be classified as:
- A. Supportive
- B. Leading
- C. Neutral
- D. Resistant
Answer: B
NEW QUESTION 14
Which of the following is an enterprise environmental factor that can influence the Develop Project Charter process?
- A. Organizational standard processes
- B. Marketplace conditions
- C. Historical information
- D. Templates
Answer: B
NEW QUESTION 15
Which process determines the risks that may affect the project and documents their characteristics?
- A. Control Risks
- B. Plan Risk Management
- C. Plan Risk Responses
- D. Identify Risks
Answer: D
NEW QUESTION 16
During which process would stakeholders provide formal acceptance of the completed project scope?
- A. Perform Quality Control
- B. Verify Scope
- C. Control Scope
- D. Develop Schedule
Answer: B
NEW QUESTION 17
When is a project finished?
- A. After verbal acceptance of the customer or sponsor
- B. After lessons learned have been documented in contract closure
- C. When the project objectives have been met
- D. After resources have been released
Answer: C
NEW QUESTION 18
How is the schedule variance calculated using the earned value technique?
- A. EV less AC
- B. AC less PV
- C. EV less PV
- D. AC less EV
Answer: C
NEW QUESTION 19
The process of identifying specific actions to be performed to produce project deliverables is:
- A. Define Activities.
- B. Create WBS.
- C. Define Scope.
- D. Develop Schedul
Answer: A
NEW QUESTION 20
Expected monetary value (EMV) is computed by which equation?
- A. Value of each possible outcome multiplied by probability of occurrence
- B. Value of each possible outcome multiplied by probability of non-occurrence
- C. Multiplying the value of each possible outcome by the probability of occurrence and adding the products together
- D. Multiplying the value of each possible outcome by the probability of non-occurrence and adding the products together
Answer: C
NEW QUESTION 21
Technical capability, past performance, and intellectual property rights are examples of:
- A. performance measurement criteria
- B. source selection criteria
- C. product acceptance criteria
- D. phase exit criteria
Answer: B
NEW QUESTION 22
Which process involves defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive plan?
- A. Direct and Manage Project Work
- B. Develop Project Management Plan
- C. Plan Quality Management
- D. Monitor and Control Project Work
Answer: B
NEW QUESTION 23
Correlated and contextualized information on how closely the scope is being maintained relative to the scope baseline is contained within:
- A. project documents updates.
- B. project management plan updates.
- C. change requests.
- D. work performance informatio
Answer: D
NEW QUESTION 24
Which of the following change requests can bring expected future performance of the project work in line with the project management plan?
- A. Corrective action
- B. Defect repair
- C. Preventative action
- D. Probable action
Answer: A
NEW QUESTION 25
A stakeholder expresses a need not known to the project manager. The project manager most likely missed a step in which stakeholder management process?
- A. Plan Stakeholder Management
- B. Identify Stakeholders
- C. Manage Stakeholder Engagement
- D. Control Stakeholder Engagement
Answer: A
NEW QUESTION 26
......