NEW QUESTION 1

Which technique is utilized in the Control Schedule process?

  • A. Performance measure
  • B. Baseline schedule
  • C. Schedule network analysis
  • D. Variance analysis

Answer: D

NEW QUESTION 2

The Perform Quality Assurance process occurs in which Process Group?

  • A. Executing
  • B. Monitoring and Controlling
  • C. Initiating
  • D. Planning

Answer: A

NEW QUESTION 3

Which tool or technique is used in Manage Stakeholder Expectations?

  • A. Stakeholder management strategy
  • B. Communication methods
  • C. Issue log
  • D. Change requests

Answer: B

NEW QUESTION 4

Which tool or technique used in the Control Procurements process can be conducted during the execution of the project to verify compliance with deliverables?

  • A. Procurement documents
  • B. Inspection and audits
  • C. Estimate budget
  • D. Risk register

Answer: B

NEW QUESTION 5

Specification of both the deliverables and the processes is the focus of:

  • A. Change control
  • B. Configuration control
  • C. Project monitoring and control
  • D. Issue control

Answer: B

NEW QUESTION 6

The process of identifying and documenting project roles, responsibilities, required skills, and reporting relationships and creating a staffing management plan is known as:

  • A. Develop Project Team.
  • B. Manage Project Team.
  • C. Acquire Project Team.
  • D. Plan Human Resource Managemen

Answer: D

NEW QUESTION 7

Which Knowledge Areas include processes from the Closing Process Group?

  • A. Project Quality Management and Project Time Management
  • B. Project Scope Management and Project Risk Management
  • C. Project Stakeholder Management and Project Cost Management
  • D. Project Integration Management and Project Procurement Management

Answer: D

NEW QUESTION 8

Which is an output from Distribute Information?

  • A. Earned value analysis
  • B. Trend analysis
  • C. Project records
  • D. Performance reviews

Answer: C

NEW QUESTION 9

Which Process Group and Knowledge Area include the Sequence Activities process?

  • A. Executing Process Group and Project Time Management
  • B. Executing Process Group and Project Cost Management
  • C. Planning Process Group and Project Time Management
  • D. Planning Process Group and Project Cost Management

Answer: C

NEW QUESTION 10

What is the name of a graphic display of project team members and their reporting relationships?

  • A. Role dependencies chart
  • B. Reporting flow diagram
  • C. Project organization chart
  • D. Project team structure diagram

Answer: C

NEW QUESTION 11

A project manager is appointed full-time to a project and is given full-time administrative staff and full-time project team members. This situation describes which type of organizational structure?

  • A. Projectized
  • B. Weak matrix
  • C. Functional
  • D. Balanced matrix

Answer: A

NEW QUESTION 12

An output of Control Schedule is:

  • A. A project schedule network diagram
  • B. A schedule management plan
  • C. Schedule data
  • D. Schedule forecasts

Answer: D

NEW QUESTION 13

Which Manage Communications tool or technique focuses on identifying and managing barriers?

  • A. Communication methods
  • B. Information technology
  • C. Communication models
  • D. Information management systems

Answer: C

NEW QUESTION 14

Which input to the Plan Risk Management process provides information on high-level risks?

  • A. Project charter
  • B. Enterprise environmental factors
  • C. Stakeholder register
  • D. Organizational process assets

Answer: A

NEW QUESTION 15

Requirements documentation, requirements management plan, and requirements traceability matrix are all outputs of which process?

  • A. Control Scope
  • B. Collect Requirements
  • C. Create WBS
  • D. Define Scope

Answer: B

NEW QUESTION 16

Funding limit reconciliation is a tool and technique used in which process?

  • A. Control Costs
  • B. Determine Budget
  • C. Estimate Costs
  • D. Control Budget

Answer: B

NEW QUESTION 17

Change requests are processed for review and disposition according to which process?

  • A. Control Quality
  • B. Control Scope
  • C. Monitor and Control Project Work
  • D. Perform Integrated Change Control

Answer: D

NEW QUESTION 18

When would resource leveling be applied to a schedule model?

  • A. Before constraints have been identified
  • B. Before it has been analyzed by the critical path method
  • C. After it has been analyzed by the critical path method
  • D. After critical activities have been removed from the critical path

Answer: C

NEW QUESTION 19

Which document describes the necessary information to determine if a project is worth the required investment?

  • A. Cost baseline
  • B. Service level agreement
  • C. Memorandum of understanding
  • D. Business case

Answer: D

NEW QUESTION 20

Who provides the inputs for the original estimates of activity durations for tasks on the project plan?

  • A. Project sponsor
  • B. Project manager
  • C. Person responsible for project scheduling
  • D. Person who is most familiar with the task

Answer: D

NEW QUESTION 21

An intentional activity to modify a nonconforming product or product component is called:

  • A. defect repair
  • B. work repair
  • C. corrective action
  • D. preventive action

Answer: A

NEW QUESTION 22

A graphic display of project team members and their reporting relationships is known as a:

  • A. Resource calendar.
  • B. Project organization chart.
  • C. Resource breakdown structure (RBS).
  • D. Responsibility assignment matrix (RAM).

Answer: B

NEW QUESTION 23

Work performance information and cost forecasts are outputs of which Project Cost Management process?

  • A. Estimate Costs
  • B. Plan Cost Management
  • C. Determine Budget
  • D. Control Costs

Answer: D

NEW QUESTION 24

A logical relationship in which a successor activity cannot start until a predecessor activity has finished is known as:

  • A. Start-to-start (SS).
  • B. Start-to-finish (SF).
  • C. Finish-to-start (FS).
  • D. Finish-to-finish (FF).

Answer: C

NEW QUESTION 25

Projects are separated into phases or subprojects; these phases include:

  • A. feasibility study, concept development, design, and prototype.
  • B. initiate, plan, execute, and monitor.
  • C. Develop Charter, Define Activities, Manage Stakeholder Expectations, and Report Performance.
  • D. Identify Stakeholders, develop concept, build, and tes

Answer: A

NEW QUESTION 26
......

P.S. Surepassexam now are offering 100% pass ensure CAPM dumps! All CAPM exam questions have been updated with correct answers: https://www.surepassexam.com/CAPM-exam-dumps.html (704 New Questions)