Free PSM-I Exam Braindumps

Pass your Professional Scrum Master I exam with these free Questions and Answers

Page 8 of 40
QUESTION 31

The IT manager asks a Development Team for a status report describing the progress throughout the Sprint. The Development Team asks the Scrum Master for advice. The Scrum Master should:
(Choose the best answer.)

  1. A. Talk to the IT manager and explain that progress in Scrum comes from inspecting an Increment at the Sprint Review.
  2. B. Tell the Development Team to figure it out themselves.
  3. C. Tell the Development Team to fit the report into the Sprint Backlog.
  4. D. Create and deliver the report to the manager herself.
  5. E. Ask the Product Owner to send the manager the report.

Correct Answer: A

QUESTION 32

Who is responsible for engaging the stakeholders?

  1. A. The Business Analyst.
  2. B. The Development Team.
  3. C. The Team Manager.
  4. D. The Project Manager.
  5. E. The Product Owner.

Correct Answer: E

QUESTION 33

The Daily Scrum is an event that happens every day. What would be three key concerns if the frequency were to be lowered to every two or three days? (Choose three.)

  1. A. Opportunities to insect and adapt the Sprint Backlog are lost.
  2. B. Impediments are raised and resolved more slowly.
  3. C. The Product Owner cannot accurately report progress to the stakeholders.
  4. D. Too much work is spent updating the Scrum board before the meeting.
  5. E. The Scrum Master loses the ability to update the Gantt chart properly.
  6. F. The Sprint plan may become inaccurate.

Correct Answer: ABF

QUESTION 34

To get started in terms of what to build, Scrum requires no more than a Product Owner with enough ideas for a first Sprint, a Development Team to implement those ideas and a Scrum Master to help guide the process.

  1. A. True
  2. B. False

Correct Answer: A

QUESTION 35

A Scrum Team has been working on a product for nine Sprints. A new Product Owner comes in, understanding he is accountable for the Product Backlog. However, he is unsure about his responsibilities. Which two activities are part of the Product Owner role according to Scrum? (Choose two.)

  1. A. Ensuring that the most valuable functionality is produced first, at all times.
  2. B. Interacting with stakeholders.
  3. C. Providing the Development Team with detailed specifications.
  4. D. Describing features as Use Cases.
  5. E. Creating detailed functional test cases.

Correct Answer: AB

Page 8 of 40

Post your Comments and Discuss Scrum PSM-I exam with other Community members: