QUESTION 6

True or False: The sprint planning is a one-day time boxed meeting divided into two 4-hour sessions?

  1. A. True
  2. B. False

Correct Answer: A

QUESTION 7

_______ constitute the Sprint Backlog and are often estimated in hours.

  1. A. Stories
  2. B. Use Cases
  3. C. Features
  4. D. Tasks

Correct Answer: D

QUESTION 8

What are the four stages of team development?

  1. A. Formin
  2. B. Stormin
  3. C. Normin
  4. D. Performing
  5. E. Lo
  6. F. Mediu
  7. G. High
  8. H. Developin
  9. I. Shapin
  10. J. Finishing
  11. K. Gatherin
  12. L. Buildin
  13. M. Developin
  14. N. Educating

Correct Answer: A

QUESTION 9

The Sprint Goal is selected before the Sprint Backlog is created.

  1. A. True
  2. B. False

Correct Answer: A

QUESTION 10

Which system provides evolutionary framework for incremental process improvement?

  1. A. Kanban
  2. B. Agile
  3. C. Poke-Yoke
  4. D. Service Management

Correct Answer: A