During the sprint review the project is assessed against the _____
Correct Answer:
A
What is the maximum duration of each Sprint planning meeting section?
Correct Answer:
C
Who defines the Sprint Backlog scope?
Correct Answer:
B
You are the Scrum Master and your Development Team of 6 members has completed six Sprints with the following information:
Sprint 1: 10 pontos
Sprint 2: 11 pontos
Sprint 3: 15 pontos
Sprint 4: 14 pontos
Sprint 5: 15 pontos
Sprint 6: 10 pontos
The remaining story points for product development total 42. What is the approximate number of Sprint required to complete product development?
Correct Answer:
B
Which of the following is not a Scrum Master responsibility?
Correct Answer:
B