QUESTION 11

- (Exam Topic 8)
Scenario:
Techniques, processes and procedures
* 1. Any threat that may result in a loss of MFH data must be escalated immediately. Joint agreements
* 2. Work is to start at the beginning of week 2 (Stage 4).
* 3. The project will take two years to complete, at an estimated cost of £2.5m. Tolerances
* 4. None.
Constraints
* 5. MFH staff must not be involved in any heavy lifting during the removal of existing IT equipment.
* 6. Installation work must take place during MFH normal working hours.
* 7. +£10,000 / -£25,000.
Reporting arrangements
* 8. Highlight Report every Monday by 10.00 am.
* 9. The report must contain a summary of all products worked on during the previous week.
* 10. Project Manager must be notified of any issues immediately by telephone. Problem handling and escalation
* 11. Impact analysis of all issues must be completed within 24 hours. Extracts or references
* 12. The Stage Plan for stage 4 is available from Project Support. Approval method
* 13. Project Assurance will review the completed Work Package and confirm completion
At the end of stage 3, the service provider will be selected and the contract awarded. During stage 4, the Account Manager for the selected service provider will work with the Project Manager to complete the transition of the services to the selected service provider.
Prince2-Practitioner dumps exhibit
Solution:
Prince2-Practitioner dumps exhibit

Does this meet the goal?

  1. A. Yes
  2. B. No

Correct Answer: A

QUESTION 12

- (Exam Topic 9)
During stage 1 the level of performance expected from the service provider was changed. After this change was agreed which of these products will require updating?

  1. A. Project Brief because this is maintained throughout the project to reflect the customer's quality expectations.
  2. B. Project Product Description because this contains details of the expected performance of the project's products.
  3. C. Quality Management Strategy because this is where all of the customer's quality expectations of the project's products should be documented.

Correct Answer: B

QUESTION 13

- (Exam Topic 8)
If Project tolerances were threatened, who needs to be notified?

  1. A. Project Board
  2. B. Project Manager
  3. C. Corporate or Programme Management
  4. D. Executive

Correct Answer: C

QUESTION 14

- (Exam Topic 1)
Project Scenario – Health and Safety Training Project:
ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.
ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver “capability to provide health and safety training”, including the materials needed for classroom-based training and e-learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.
The e-learning course will be developed by a specialist external consultancy. The materials for
classroom-based training will be delivered by ABC Company’s development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.
The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered. ABC Company is planning to deliver pilot courses within five months of starting the project.
The ABC Company standard development model for new courses recommends the following stages:
Prince2-Practitioner dumps exhibit
End of the Project scenario. Additional Information:
The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.
The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.
The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.
The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company’s IT manager reports to the Operations Director.
The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.
The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.
The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.
The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.
The Corporate Document Manager reports to the Central Services Director. She helped establish the company’s document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.
The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.
End of the additional information. STARTING UP A PROJECT
Here are three actions carried out during the ‘starting up a project’ process. As part of which activity (A-F) should each action occur?
Choose only one activity for each action. Each activity can be used once, more than once, or not at all.
Prince2-Practitioner dumps exhibit
Solution:
Prince2-Practitioner dumps exhibit

Does this meet the goal?

  1. A. Yes
  2. B. No

Correct Answer: A

QUESTION 15

- (Exam Topic 12)
During the 'create the project plan' activity as part of the initiation stage, the project manager identifies several threats to the project timescales. These threats relate to stage 3 products. Therefore, the project manager decides to wait until the end of stage 2 to assess the risks to the project plan.
Is this an appropriate application of the plans theme, and why?

  1. A. Yes, because detailed planning of stage 3 should take place after completion of the stage 2 products.
  2. B. Yes, because risk planning should take place in the stage plan before the risks occur, not in the projectplan.
  3. C. No, because the risks inherent in the project plan should be assessed, and the plan modified to manage them.
  4. D. No, because the risk actions to manage project-level threats should be recorded in the risk register.

Correct Answer: C
Reference https://books.google.com.pk/books?id=CSm7x74Px94C&pg=PA181&lpg=PA181&dq=prince2+risks+inherent+

Page 4 of 57

Post your Comments and Discuss PRINCE2-Exams PRINCE2-Practitioner exam with other Community members: