QUESTION 21

- (Exam Topic 7)
Scenario:
The Ministry of Food Hygiene (MFH) has a quality management system which contains a document control process to manage all documentation requirements. The document control process was created by the MFH Quality Manager, who now maintains all of MFH's documents and performs an organization-wide configuration management role. The MFH Quality Manager will administer the configuration management procedure for the Restructuring project since this must comply with the MFH document control process.
Having created the Issue Report and analyzed the impact of removing the Facilities Division from the scope of the Outsourcing project, the proposed option exceeds tolerance. Nhat is the next action the Project Manager should consider?

  1. A. Create an Exception Report to inform the Project Board of the situation and the available options.
  2. B. Update the associated Configuration Item Records with details of the Issue Report that caused the change.
  3. C. Amend the Stage Plan for stage 3: remove all products related to the Facilities Division and add the activities required to deliver the new Government initiative.
  4. D. Create an Exception Plan to change all of the project's products to reflect the exclusion of services provided by the Facilities Division.

Correct Answer: A

QUESTION 22

- (Exam Topic 2)
Scenario
Additional Information
During the initiation stage the Project Manager met with the Marketing Director to find out more about the requirements of the promotional calendar and recorded the following notes:
There has been a reduction in the order numbers at the MNO Manufacturing due in part to the increased marketing activities of its competitors. 10% of customers have not re-ordered in this financial year and staff morale is poor. A number of skilled staff have left as a result and replacement staff have not been recruited due to the reduced operation. If the project is successful, a recruitment campaign will be required to fill the existing staff vacancies and there may be a requirement for additional staff. Operational costs are likely to increase because skilled staff are expensive and difficult to find.
In financial terms, there were a total of 1,500 orders in the last financial year, each with an average profit of
£2k. The Marketing department believes that sending a promotional calendar to our current and prospective customers would increase orders by at least 10% with a minimum of 10 further orders from the list of prospective customers within 12 months from the date of distribution.
The Marketing Director will be funding the project from the business marketing budget. She believes that the effect of a good company image portrayed by a successful calendar would last into a second year. She has forecast the same increase in orders for a second year and predicts that the annual employee satisfaction survey will show a measurable improvement in staff morale.
A number of alternatives were explored, including:
Prince2-Practitioner dumps exhibit 20% discount for all repeat customers - not cost-effective and very short term
Prince2-Practitioner dumps exhibit A promotional calendar as a free Christmas gift - would target current and prospective customers and the benefits would last into a second year
Prince2-Practitioner dumps exhibit A series of television and press advertisements was too expensive
Prince2-Practitioner dumps exhibit A direct mail shot to all customers - benefit would be short term
Prince2-Practitioner dumps exhibit Creation of an internet website - would not suit all customers
The calendar is seen as the favored option, as long as the company's competitors do not increase their marketing activity. Whilst the Marketing department wants a very high quality, glossy product, the project management team must be aware of the cost this will incur.
Using the Project Scenario and the additional Information provided for this question In the Scenario Booklet, answer the following question.
Which 2 statements should be recorded under the Reasons heading?

  1. A. The Marketing department believes that sending a promotional calendar to current and prospective customers will increase orders by at least 10%.
  2. B. 10% of customers have not re-ordered in this financial year.
  3. C. 1,500 orders are expected, each with an average profit of £2k.
  4. D. The Marketing department believes that the effect of a good company image, portrayed by a successful calendar, will last into a second year.
  5. E. MNO Manufacturing is experiencing a fall in orders due in part to the increased marketing activities of its competitors.

Correct Answer: BE

QUESTION 23

- (Exam Topic 5)
Scenario
Product Summary
A list of customers will be collated. This will use existing information from the Accounts department about current customers, and existing information from the Marketing department about prospective customers.
Using the tariff of mailing costs available from the Post Office, a production cost forecast will be produced to allow the CEO and the Marketing Director to decide whether to continue with the project. If they decide to continue, they will give the approval to launch the internal label design competition. Competition rules will be required to communicate details of the competition to the staff. The chosen label design will then be selected from the competition entries.
The photos for the calendar must be based on existing photo design ideas available from the Marketing department. The selected photos will be chosen from these. Monthly calendar displays will be created to show the required layout of each page.
Product Breakdown Structure (contains errors)
Prince2-Practitioner dumps exhibit
Extract from Stage Plan for stage 3.
(All entries are true statements but may not be shown under the correct heading or in the correct document).
Prince2-Practitioner dumps exhibit
Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional intonation for this question in the Scenario Booklet, answer the following 5 questions.
The Stage Plan for stage 3 has been produced.
The Engineering Manager insists that there are to be no interruptions to operations whilst photographs are being taken of the engineering staff performing their everyday duties and operating machinery. Two weeks ago the professional photographer produced the photo session schedule based on the operational staff schedule. The operational staff schedule is produced weekly and maintained by the Engineering Manager.
None of the £500 change budget has been used to date and this is available for the stage. Which 2 statements apply to the Planning assumptions section?

  1. A. No change to entry 8 because this cannot be confirmed until all of the label designs entries have been received and an assessment made.
  2. B. Move entry 8 to External dependencies because the label designs are created outside of the scope of the project.
  3. C. Delete entry 9 because the photo session schedule should have been approved as part of stage 2.
  4. D. Move entry 9 to External dependencies because the photo session schedule is created by the professional photographer.
  5. E. Delete entry 10 because the inclusion of different members from the Engineering team in each photo should be shown in the Product Description for the photos.

Correct Answer: AE

QUESTION 24

- (Exam Topic 9)
Who is responsible for the initial creation of the Configuration Item records?

  1. A. Project Manager
  2. B. Team Manager
  3. C. Project Assurance
  4. D. Project Support

Correct Answer: D

QUESTION 25

- (Exam Topic 4)
Scenario
Additional Information Product Description
Prince2-Practitioner dumps exhibit
Quality notes from the Daily Log
The Director of Information Technology Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review future job descriptions of the transferred staff before the final contract is signed with the selected service provider.
The service level agreement between MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry standards for providing outsourced services.
MFH has a quality management system which contains a document control procedure for all its documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a formal approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors) Introduction
* 1. This document defines the approach to be taken to achieve the required quality levels during the project.
* 2. The Project Board will have overall responsibility for the Quality Management Strategy.
* 3. Project Assurance will provide assurance on the implementation of the Quality Management Strategy. Quality management procedure - Quality standards
* 4. The selected service provider will operate to industry standards for providing outsourced services.
* 5. MFH document standards will be used. Records
* 6. A Quality Register will be maintained to record the planned quality events and the actual results from the quality activities.
* 7. Configuration Item Records will be maintained for each product to describe its status, version and variant.
* 8. Approval records for products that require them will be stored in the quality database. Roles and responsibilities
* 9. The DIT will check that the employment contracts for outsourced staff adhere to employment law.
* 10. Team Managers will provide details of quality checks that have been carried out.
* 11. Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process.
* 12. The Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved.
None of the reviewers have proof-reading skills.

  1. A. Record an action to request that Project Assurance identify a proof-reader who can, within the next 2 days, complete the check for typographical errors.
  2. B. Ask the reviewers present at the meeting to conduct a proof-reading exercise and pass any comments to the author within 2 days.
  3. C. Contact Project Assurance to find appropriate resources to come into the review.
  4. D. No action required.

Correct Answer: A

Page 6 of 57