- (Exam Topic 2)
The Chief Executive Officer (CEO) has announced that the hardware division will be sold to another company.
The sale of this division is an example of which of the following?
Correct Answer:
D
- (Exam Topic 3)
Which of the following indicators would help the project manager to determine the financial status of the project?
Correct Answer:
C
Reference:
https://pmstudycircle.com/planned-value-pv-earned-value-ev-actual-cost-ac-analysis-in-project-cost-managemen
- (Exam Topic 3)
In which of the following circumstances would faxing be the MOST appropriate communication method?
Correct Answer:
D
- (Exam Topic 2)
Tasks B and D start after Task A is completed. Task C starts after Tasks B and D are completed. task E starts after Task D is completed. Task H starts after task B is completed. Task G starts after Tasks C and H are completed. Task F starts after Task E is completed.
Following are the durations of all tasks:
Task Duration
A) Four weeks
B) Two weeks
C) Six weeks
D) Three weeks
E) Seven weeks
F) One week
G) Two weeks
H) Nine weeks
Which of the following tasks are on the critical path?
Correct Answer:
B
- (Exam Topic 3)
A project team is preparing for a major system upgrade that is scheduled for next week. During the upgrade, there will be limited availability of technology resources.
Which of the following is the BEST communication method for the team during the activation?
Correct Answer:
D
Instant messaging allows you to communicate with another person via a text message over the Internet. There are many software programs that provide this capability. You can use instant messaging on a computer, tablet, or phone provided the software program you’re using has that capability. It’s a great mechanism to convey a quick, short message. Instant messaging isn’t appropriate for meetings or complex information or for communicating with multiple people at the same time.