QUESTION 26

- (Exam Topic 2)
Due to a lack of adherence to the risk response plan, there are numerous safety concerns within the scope of a building project.
Which of the following MOST likely explains this issue?

  1. A. Risks were not identified.
  2. B. Risks were not mitigated.
  3. C. Risks were not exploited.
  4. D. Risks were not communicated.

Correct Answer: D

QUESTION 27

- (Exam Topic 3)
There is friction between team members who were on the team before a merger took place and those who transitioned during the merger. This situation is having an adverse effect on team performance. Which of the following can the project manager do to help resolve this issue?

  1. A. Observe the team during the transition period and give the team time to form.
  2. B. Engage in relationship building by getting both sides to work on tasks together.
  3. C. Report the conflict to human resources and let them address it.
  4. D. Assign tasks between the team members to ensure interaction is limited.

Correct Answer: B

QUESTION 28

- (Exam Topic 1)
A project team has finished creating a WBS and started developing a schedule. The team should FIRST determine the:

  1. A. durations.
  2. B. tasks.
  3. C. critical path.
  4. D. resources.

Correct Answer: B

QUESTION 29

- (Exam Topic 2)
A PM receives notification that an issue will impact a deliverable on the critical path. The issue is logged with a unique ID and assigned to a team member; however, the team member has not addressed it after a week. Which of the following would be the BEST approach to resolving the issue?

  1. A. Assign a different team member to resolve the issue before the next status meeting.
  2. B. Review the issue with the assigned team member to determine a due date.
  3. C. Set a due date to resolve the issue and inform the assigned team member.
  4. D. Report the team member to a functional manager for disciplinary action.

Correct Answer: B

QUESTION 30

- (Exam Topic 1)
An outsourced project team member approaches the project manager and complains that the contract does not permit overtime. The project manager had fast-tracked tasks that require additional hours. Which of the following documents did the project manager fail to reference?

  1. A. MOU
  2. B. MOA
  3. C. SOW
  4. D. SLA

Correct Answer: B