QUESTION 21

- (Exam Topic 3)
A project manager in a function organization is resource leveling the upcoming phase. The project manager notices one of the resources is assigned with 20% of allocation to a secondary project. This situation limits and jeopardizes the commitment date.
Which of the following should the project manager do NEXT?

  1. A. Ask the PMO to mitigate the risk related to insufficient resources.
  2. B. Ask the functional manager to provide a resource with the same level of allocation.
  3. C. Remove 20 of allocation of the resource from the secondary project.
  4. D. Ask the resource to improve performance to target with commitment date.

Correct Answer: C

QUESTION 22

- (Exam Topic 2)
A vendor was removed from a company due to non-performance but continues to submit invoices for work that was not completed. Which of the following should the project manager do to stop the vendor from sending invoices?

  1. A. Draft a C&D letter and send it to vendor.
  2. B. Review the MOU with the vendor.
  3. C. Ask the legal departments to draft a non-complete agreement for the vendor to sign.
  4. D. Meet with the finance department to prevent the vendor from sending invoices.

Correct Answer: A

QUESTION 23

- (Exam Topic 2)
A company is in the process of combining the human resources and marketing departments. Which of the following describes this change?

  1. A. Business process change
  2. B. Business merger
  3. C. Internal reorganization
  4. D. Interorganizational change

Correct Answer: A

QUESTION 24

- (Exam Topic 1)
A governance committee has just approved a new project. The project scheduler is now developing the project schedule. Which of the following activities should be done FIRST?

  1. A. Add durations.
  2. B. Add the start and finish dates
  3. C. Add tasks.
  4. D. Add resources.

Correct Answer: C

QUESTION 25

- (Exam Topic 3)
A concrete pad needs to be laid for a new house and requires three days to cure. The project manager notes that rain may be in the immediate forecast.
Which of the following would BEST avoid the risk of rain damage?

  1. A. Place a tarp over the fresh concrete to protect it.
  2. B. Refinish the concrete if it rains during that time.
  3. C. Pour the concrete as quickly as possible to allow the most drying time.
  4. D. Wait to pour the concrete until rain is not in the forecast.

Correct Answer: C