QUESTION 6

- (Exam Topic 1)
new stakeholder has been added to a project with a BAG of $850,000. The stakeholder has raised five change requests to the CCB; two of them have been approved, and three are awaiting initial review. Considering the project has a CPI of 0.89 and an SPI of 1.14, and the approved ones will be implemented, which of the following should the project manager do LAST?

  1. A. Identify and document the risk.
  2. B. Evaluate the impact and justification.
  3. C. Implement the change.
  4. D. Update the documents and plans.

Correct Answer: D

QUESTION 7

- (Exam Topic 2)
A project manager receives a call from the area regional building department and is informed that, upon inspection, waterlines from public water access to the project building do not meet local material and installation code specifications. Which of the following items BEST describes the unmet objective?

  1. A. Schedule
  2. B. Milestone
  3. C. Gate
  4. D. Task

Correct Answer: D

QUESTION 8

- (Exam Topic 3)
A customer approaches a team member to report that old functionality is no longer valid due to technology restrictions. The team member has also noticed this during the execution of the project. The team member
agrees with the new functionality provided by the customer, implements the change, and notifies the project manager.
Which of the following actions should the project manager take NEXT?

  1. A. Notify the team that the change has been made.
  2. B. Update the project management plan based on the change.
  3. C. Proceed to the next task in the project schedule.
  4. D. Conduct an impact analysis to verify there is no collateral damage.

Correct Answer: C

QUESTION 9

- (Exam Topic 3)
Adhering to the project budget is MOST important during which of the following project phases?

  1. A. Planning
  2. B. Initiating
  3. C. Monitor and controlling
  4. D. Closing

Correct Answer: C

QUESTION 10

- (Exam Topic 1)
A project manager provides status reports to a customer on a biweekly basis, but the customer is very busy and only has a few minutes to review the project.
Which of the following are critical for the project manager to provide?

  1. A. Cost, schedule, organizational chart, and risks/issues
  2. B. Risks/issues, cost, RACI chart, and action items
  3. C. Schedule, cost, risks/issues, and milestones
  4. D. Action items, organizational chart, schedule, and NDA

Correct Answer: C