- (Exam Topic 1)
new stakeholder has been added to a project with a BAG of $850,000. The stakeholder has raised five change requests to the CCB; two of them have been approved, and three are awaiting initial review. Considering the project has a CPI of 0.89 and an SPI of 1.14, and the approved ones will be implemented, which of the following should the project manager do LAST?
Correct Answer:
D
- (Exam Topic 2)
A project manager receives a call from the area regional building department and is informed that, upon inspection, waterlines from public water access to the project building do not meet local material and installation code specifications. Which of the following items BEST describes the unmet objective?
Correct Answer:
D
- (Exam Topic 3)
A customer approaches a team member to report that old functionality is no longer valid due to technology restrictions. The team member has also noticed this during the execution of the project. The team member
agrees with the new functionality provided by the customer, implements the change, and notifies the project manager.
Which of the following actions should the project manager take NEXT?
Correct Answer:
C
- (Exam Topic 3)
Adhering to the project budget is MOST important during which of the following project phases?
Correct Answer:
C
- (Exam Topic 1)
A project manager provides status reports to a customer on a biweekly basis, but the customer is very busy and only has a few minutes to review the project.
Which of the following are critical for the project manager to provide?
Correct Answer:
C
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 326