QUESTION 11

- (Exam Topic 3)
Which of the following is the MOST likely trigger to update the project risk register?

  1. A. An issue occurs.
  2. B. A quality audit is passed.
  3. C. A project milestone is completed.
  4. D. A stakeholder initiates a change request.

Correct Answer: A

QUESTION 12

- (Exam Topic 1)
A project manager has noticed poor attendance as status meetings.
Which of the following strategies should the project manager use to improve attendance? (Choose two.)

  1. A. Provide an agenda before the status meeting.
  2. B. Adhere to an agenda and scheduled time.
  3. C. Add non-project-related items to the agenda.
  4. D. Add and discuss new agenda items throughout the meeting.
  5. E. Discard the action items at the conclusion of the meeting.

Correct Answer: AB

QUESTION 13

- (Exam Topic 2)
A project team is not delivering their tasks in a timely manner. Additionally, tasks are being reworked because requirements continue to be identified as work packages are being delivered.
Which of the following are NOST likely missing from the project? (Select two.)

  1. A. Project charter
  2. B. Organizational chart
  3. C. Scope document
  4. D. Status report
  5. E. Business case
  6. F. Project plan

Correct Answer: CF

QUESTION 14

- (Exam Topic 1)
A project manager is assigned to a new project that must start immediately. No formal or approved documents have been authored for the project. The project manager must identify project roles, justify the business need, and determine project scope boundaries.
Which of the following documents should the project manager create?

  1. A. Business case
  2. B. Project charter
  3. C. Scope statement
  4. D. Project management plan

Correct Answer: B
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 107

QUESTION 15

- (Exam Topic 2)
An employee is assigned to a project and is developing a project charter. Which of the following are some of the constraints the employee would typically face at this stage of the project?

  1. A. Environment, resources, requirements, and quality
  2. B. Budget, quality, resources, and schedule
  3. C. Deliverables, scope, and budget environment
  4. D. Budget, scope, quality, and schedule

Correct Answer: D