QUESTION 1

- (Exam Topic 3)
A project is due to deliver, configure, and install a collection of medical devices. The first device in the collection is reportedly four weeks behind schedule is manufacturing. Which of the following BEST describes how the project manager can keep the project on track?

  1. A. Expedite shipping of the first item to keep the installation order.
  2. B. Rearrange the installation dates since other devices are already on site.
  3. C. When the late equipment arrives, have the team work overtime.
  4. D. Explain the vendor payments will be withheld if delivery is not met.

Correct Answer: B

QUESTION 2

- (Exam Topic 3)
Halfway through a project, the project manager is told it needs to be completed four weeks earlier than originally planned. Which ot the following will MOST likely be impacted to accomplish this goal?

  1. A. Risks
  2. B. Budget
  3. C. Quality
  4. D. Deliverables

Correct Answer: C

QUESTION 3

- (Exam Topic 1)
The project manager has had a large number of change requests approved by the project steering committee, but has been given no extra time to deliver the project.
Which of the following schedule compression techniques should be used by the project manager?

  1. A. Rescheduling
  2. B. Crashing
  3. C. Rebaselining
  4. D. Control scope

Correct Answer: B

QUESTION 4

- (Exam Topic 3)
A construction company is building a plant in a territory that is prone to earthquakes. To address the risk and consequences of potential earthquakes during and after plant construction, the company purchases additional insurance. Which of the following risk responses has occurred?

  1. A. Avoiding
  2. B. Mitigating
  3. C. Accepting
  4. D. Transferring

Correct Answer: D

QUESTION 5

- (Exam Topic 3)
Deliverables are repeatedly delivered late by one project team. The project manager has consulted with the functional manager but has not been able to make progress on the expectations. Which of the following would BEST help the project manager to communicate the continued issue?

  1. A. Communication plan
  2. B. Scope document
  3. C. Status report
  4. D. RACI matrix

Correct Answer: C